How License to Sell Delays Could Affect Cebu’s Property Market

License to Sell in the Philippines

The Cebu property market continues to see demand for residential properties, but delays in securing government approvals are creating challenges for developers preparing new projects.

A recent report by The Freeman highlighted concerns from property industry representatives about delays in the issuance of Licenses to Sell (LTS). The permit is required before developers can legally market and sell subdivision lots and condominium units, making it an important step before a pre-selling project can officially enter the market.

What Is a License to Sell?

A License to Sell is an approval issued by the Department of Human Settlements and Urban Development (DHSUD) that allows a qualified residential development to be marketed and sold.

This is particularly important for pre-selling properties. Developers generally need to secure the required approval before offering condominium units or subdivision lots for sale.

Because of this, delays in LTS processing can affect more than a project’s launch date. They can also influence when developers can begin generating sales from new inventory and when buyers gain access to additional housing options.

Why Are Developers Concerned About Delays?

According to Cebu Landmasters Inc. President and CEO Franco Soberano, delays in obtaining LTS approvals had disrupted roughly a year’s worth of the company’s planned launches.

The company said the delays limited the amount of new residential inventory it could bring to the market. Soberano also pointed to the wider economic effects, including fewer construction-material orders and fewer jobs associated with projects that have been delayed.

Industry representative Anthony Leuterio separately said the pace of LTS approvals had fallen significantly compared with 2025. Colliers Philippines also identified LTS processing as a regulatory concern for the residential market, noting that developers cannot legally market projects without the required license.

These are industry assessments, rather than an indication that every residential project in the country is experiencing the same delay.

How Could Permit Delays Affect Housing Supply?

The main concern is the timing of new housing inventory.

If developers are ready to launch projects but cannot secure the required approvals, those projects may remain outside the active market for longer. This can reduce the number of new units available to buyers during a particular period.

Colliers’ Joey Roi Bondoc said slower approvals could restrict the number of projects entering the market and potentially add pressure to residential prices, particularly as developers also face higher land and construction costs.

For buyers, the practical issue is straightforward: fewer newly launched projects can mean fewer choices in terms of location, unit type and price range.

Cebu’s Residential Market Could Feel the Impact

The issue is particularly relevant to Cebu because the province and wider Metro Cebu area continue to see residential development across different market segments.

Cebu Landmasters, for example, said it was preparing to accelerate several delayed launches after changes to the LTS review process. The company expected to launch four projects, including Alto in Cebu, residential developments in Ormoc and Bogo, and an economic housing project in southern Cebu.

The company’s planned launches illustrate how regulatory approval can directly affect the timing of new residential supply.

At the same time, the situation should not be interpreted as meaning that Cebu’s entire housing pipeline has stopped. Developers continue to build and launch projects, while the effect of approval delays varies depending on the project and its regulatory status.

DHSUD Has Also Provided a Different Perspective

The issue has generated differing assessments between industry groups and regulators.

In June, DHSUD Central Visayas rejected claims that permit delays were holding back approximately 10,000 housing units in the region. The agency said only two LTS applications remained pending in Central Visayas at that time and stated that some applications cited by industry stakeholders had either received notices of deficiency or were awaiting additional documentation from developers.

DHSUD also emphasized that permit reviews are necessary to ensure compliance with housing regulations and protect buyers, particularly in the pre-selling market.

This distinction is important when looking at the issue. Industry representatives have raised concerns about processing speed, while DHSUD has said that its review process is intended to maintain regulatory compliance and that some pending applications involve additional requirements.

The Effect on Developers and Construction

LTS delays can also affect the timing of a developer’s business operations.

A project waiting for approval may have capital committed to planning, land acquisition, design and other preparations without being able to proceed with its full sales launch.

Once construction begins, delayed launches can also affect the timing of material procurement, contractor activity and employment.

For the broader economy, this means regulatory processing can have effects beyond the developer itself. Residential construction involves contractors, engineers, architects, suppliers, brokers, workers and other businesses that depend on project activity.

What Does This Mean for Property Buyers?

For buyers considering a pre-selling property, an LTS is an important part of the project’s regulatory status.

Buyers should confirm that a development has the required approvals before making a purchase decision and should work with legitimate developers and licensed real estate professionals.

It is also useful to distinguish between a project that has been announced and a project that is already legally available for sale. A developer may announce a future development before all regulatory requirements have been completed, but the ability to formally market and sell residential units depends on the applicable approvals.

This makes regulatory status an important part of due diligence, alongside the developer’s track record, location, pricing, payment terms, construction schedule and other project details.

What Happens Next?

The immediate outlook depends partly on whether LTS processing becomes faster and more consistent.

Cebu Landmasters said the return to a decentralized review system could help improve processing times and allow the company to restart delayed launches. The company expected to bring new residential inventory to the market after the approval bottleneck.

For Cebu buyers, the development of this situation is worth monitoring because faster approvals could bring additional projects and unit choices into the market, while prolonged delays could affect the timing of new residential supply.

The issue ultimately highlights an important part of the property market that buyers do not always see: before a condominium or subdivision reaches the sales stage, developers must navigate regulatory requirements that can influence when and how new housing inventory reaches the market.